top
Home Vision BOM Functions of QIE Committees Organization Map of QIE Progress QIE Directory Contact
News & Updates
 
  Computerization of Property Record
  Fire Brigade saves losses in millions
  Labour Canteen for factory labours
  Main Gates and Barriers are installed to reduce security risk
  Fire Brigade saves losses in millions
Links

    Punjab Industrial Estate

    Punjab Government

    Lahore Chamber of Commerce &     Industry

    Constitution of Pakistan

    Ministary of Commerce

    Lahore Development Authority

    More...
 

Infrastructure Development Work

FUNCTION OF QIE
   Infrastructure Development
   Property & Legal Matters
   Building Plans
   Security Services
   Solid Waste Management
   Fire Brigade Station

Quaid-e- Azam Industrial Estate is one of the largest planned Industrial Estates of Punjab, spread over an area of 565 acres. It has 477 industrial plots of the sizes varying from 1 kanal to 10 kanals.

The initial infrastructure had become overloaded that necessitated development works in such a way that the new works needed to be interwoven with the existing works. This gave a peculiar dimension to financial planning and management. Cost and time constraints were additional considerations. Health and safety of the existing population during execution of the works were to be ensured.
Infrastructure Development consisted of two phases because of reasons

    • Availability of fund given by Government of Punjab and
    • Enabling regular flow of Traffic of   industrial activities

DEVELOPMENT WORK PHASE-1

The infrastructure development commenced on September 02.2006 in small industrial area. The scope of works includes water supply, over head water tank, drainage, roads ,sewerage system, landscaping and street lighting. Construction works have almost been completed. Landscaping will be start on completion of all other activities. Its overall progress is about 95%. The cost of phase-1 is 200 million.

Scope of Development Phase I

Scope of Work

Amount (PKR)

1

   Water supply net work                   

16.92 Millions
2    Sewerage system                             86.90“
3    Drainage 10.78 “ 
4    Roads  72.37 “
5    Street Lighting   03.82“
6  Land Scaping 01.57“
Total PKR    192.36      Millions

Construction works of phase -1, such as   water supply, Drainage and Roads   and sewerage system have almost been completed. Landscaping   not yet started. Street Lighting work 70 % have also   been completed.

DEVELOPMENT WORK PHASE-1

The infrastructure development of Phase-2 has already been undertaken on 18 Oct 2007 in Main Industrial Area. The scope of work is comprised of drainage system, roads and with 2 main entrance gates and 11 kiosks for factory workers. Overall 60% work has also been completed. The cost of Phase-2  is 141 millions.

Construction works of   phase -11   have already been under taken since 18.10.2007.

Scope of Development Phase II

Scope of Work

Amount (PKR)

1 Denim road   Rs.58.00 millions
2 Shan road   Rs.23.00 '
3 Service road Rs.19.00 '
4 Denim new Drain Rs.10.00 '
Total PKR    110.00 millions
 
 
Home  |  Vision  |  BOM  |  Functions of QIE  | Committees  |  Organization  |  Map of QIE  |  Progress  |  QIE Directory  |  Contact
Property |  Legal | Building Authorization | Security Services | Solid Waste & Sanitation | Fire Brigade Station | Development Works
QIE, All Rights Reserved © 2008